New TopShim run:

version = topshim 4.4.1
date = 2025-01-09
time = 15:08:36.165
command = topshim 

FINE SHIMMING

Parameters:

probe = Z166552_0019
solvent = CDCl3
shim nucleus = 2H
nucleus optimised for = 1H
o1p (from lock) = 7.24 ppm

Results:


1D Shimming:
Iteration 1: FWHM Before= 6.1 Hz, Target= 0.4 Hz, After= 0.8 Hz
Iteration 2: FWHM Before= 0.8 Hz, Target= 0.4 Hz, After= 0.9 Hz
Iteration 3: FWHM Before= 0.9 Hz, Target= 0.3 Hz, After= 0.6 Hz
Iteration 4: FWHM Before= 0.6 Hz, Target= 0.4 Hz, After= 0.6 Hz
Iteration 5: FWHM Before= 0.6 Hz, Target= 0.3 Hz, After= 0.5 Hz
Iteration 6: FWHM Before= 0.5 Hz, Target= 0.5 Hz, After= 0.6 Hz
Iteration 7: FWHM Before= 0.6 Hz, Target= 0.5 Hz, After= 0.4 Hz
Shim succeeded

Lineshape quality factor (1D spectrum, spinning) = 0.559

shim changes: 
Z	+129
Z2	-9
Z3	+30
Z4	-112
Z5	+91

duration = 1 min 40 sec
completed successfully
finished Thu Jan  9 15:10:15 2025


========================================================================