New TopShim run:

version = topshim 2.0.0
date = 2024-07-10
time = 13:31:28.372
command = topshim 

FINE SHIMMING

Parameters:

probe = Z104275_0301
solvent = CDCl3
shim nucleus = 2H
nucleus optimised for = 1H
o1p (from lock) = 7.24 ppm

Results:


1D Shimming:
Iteration  1: FWHM Before= 0.4 Hz, Target= 0.3 Hz, After= 0.7 Hz
Iteration  2: FWHM Before= 0.7 Hz, Target= 0.5 Hz, After= 0.7 Hz
Iteration  3: FWHM Before= 0.7 Hz, Target= 0.4 Hz, After= 0.5 Hz
Shim succeeded

Lineshape quality factor (1D spectrum, spinning) = 0.545

shim changes: 
Z	+5
Z2	+7
Z3	-91
Z4	-150
Z5	+650

duration = 2 min 19 sec
completed successfully
finished Wed Jul 10 13:33:46 2024


========================================================================